The paving is done. The only remaining tasks are to finish landscaping (fix the grass), put sealer between concrete gutter and pavement, and hang the fence.

The road was paved by B&W Paving, overseen by the Elizabeth Field airport consultant and engineer C&S Engineers, and paid for with a grant from the FAA. Gordon Murphy orchestrated the project on behalf of the Ferry District, representing the Town of Southold that is the owner of the airport.

The road was built to FAA specifications. Twelve inches of base material was removed and the twelve inches was replaced.